Login  |  Register
 
Wednesday, September 08, 2010
You are here :: Common Area Improvement
Common Area Improvement Project Minimize

Heritage Greens Common Area Improvement Project - update August 30

Select the following links to access the architectual drawings. 

Click for Site Plan Drawing-Draft

Click for View1

Click for View2

Click for View3

Click for a perspecitve to view the current pool layout compared to the proposed layout PDF

Click for another new drawing PDF

Email the HOA Common Area Project Committee with requests and comments at:  poolcomments@heritagegreens.org

(NEW) Project Status Update:

Many of your neighbors and retained professionals have been working hard over the past several months on the Common Area Improvement Project.  We are still on schedule to commence construction after Labor Day . . . just a couple weeks from now.

 

Here is an update on the progress being made.

 

 

General Contractor Selection Process:

 

Eight (8) General Contractors were short-listed to receive the Request for Proposal (RFP) based upon a review of the 22 contractor responses received to the RFQ.

 

One (1) General Contractor declined to bid prior to the issuance of RFP and Construction Bid Documents B Pinkard Construction.  During the bid process 2 additional General Contractors made a decision to not respond to the RFP B Waner Construction and Adolfson & Peterson.

 

On Friday, August 6, 2010, the following bids were received:

 

Milender White Construction             $2,220,448

White Construction Group                 $2,238,000

Taylor Kohrs                                       $2,430,384

Hyder Construction                            $2,558,000

Centerre Construction                         $2,750,330

 

All bids received were slightly above the preconstruction estimate provided by Waner Construction on March 23, 2010. This increase is due to the additional design details incorporated into the early SD drawings used for pricing and the following increases/changes in scope:

 

·         Landscape and irrigation of entire site          

·         Grading/Stormwater Detention Pond required by SEMSWA

·         Parking lot milling and resurfacing

·         Kids sprayground size increase and change from wading pool         

·         Stairs and ramp to front entry due to grading issues

·         3 additional toilets in women’s bathroom due to City of Centennial comments

·         Radiant heating under sidewalk at north side of building

·         Grill area enhancements         

 

 

Budget:

 

The sale of bonds resulted in the availability of approximately $2,680,000 for the project. Taking a conservative approach, the estimated budget set by the Metro District was $2,500,000, inclusive of all design and project management fees.  After deducting the estimate fees and other non-construction costs, the estimated budget for construction was $2,071,911. 


 

The owner’s representative, Mark Degenaars, hired by the Metro District recommended the board conduct interviews with Milender-White and White Construction.  Prior to the interview, each prospective General Contractor was requested to provide a list of voluntary value engineering items for review and consideration. The following topics were discussed during the interview with each firm:

 

·         Review RFP response

·         Review proposed lump sum fee for General Conditions

·         Review proposed subcontractors and project buyout approach        

·         Discuss schedule and approach with proposed project team

·         Review voluntary value engineering items                            

·         Review project alternates                               

·         Discuss value engineering options provided by Studio DH

 

The pre-construction schedule allowed for the Final General Contractor recommendation to be presented to the Metro District by Monday, August 16, 2010.  Interviews were held with Milender-White and White to review their RFP response/bid, project team, schedule and any potential value engineering options. Based on those interviews, the MD is now in the process of negotiating fees with Milender-White, meeting with subcontractors and obtaining hard numbers for all VE options. After finalizing a path or paths to get the project in line with the budget, a laundry list of VE items will be presented to the Metro District for review. Upon completion of that review, the Metro District will provide the entire list to the HOA Design Committee.  The intention is to have this process completed by August 27, 2010.

 

 

Construction:

 

The schedule remains intact to begin mobilization the day after Labor Day and commence construction on Monday, September 13th.  Once the VE options are reviewed and decided upon, there will be a review of the overall schedule, site logistics and work times so that the HOA can properly inform the neighborhood and manage expectations.

 

The realistic goal remains of having the project completed prior to the Memorial Day Weekend 2011.

 

More to follow in the coming days/weeks . . . .

Home | Common Area Improvement | Neighborhood Info | Architectual Committee | Gators Swim Team
Privacy Statement  |  Terms Of Use
 
Copyright 2008-2010 Heritage Greens HOA